ISTQB ATM Cert Guide PDF 100% Cover Real Exam Questions [Q12-Q27]

Share

ISTQB ATM Cert Guide PDF 100% Cover Real Exam Questions

Pass ATM Exam - Real Questions and Answers

NEW QUESTION # 12
Assume that you are the Test Manager for a small insurance application development
project.
You have decided to adopt a risk-based testing strategy: 5 product risks (R1, R2, R3, R4,
R5) have been identified and their levels of risk have been assessed. 10 test cases (T1, ...,
T10) have been designed to cover all the product risks.
The following table shows the risk level and the test cases associated to the identified
product risks (higher risk level means higher risk):
You are not confident with the assessment of the risk level and you suspect that it will be
possible to find high-priority bugs in low-risk areas.

Furthermore the period for test execution is very short. Your goal is to test all the product
risks in a risk-based way, while assuring that each product risk gets at least some amount
of testing.
Which of the following answers describes the best test execution schedule in this scenario?
K3 2 credits

  • A. T1, T2, T3, T4, T5, T6, T7, T8, T9, T10
  • B. T10, T8, T6, T4, T2, T9, T7, T5, T3, T1
  • C. T1, T3, T5, T7, T9, T2, T4, T6, T8, T10
  • D. T10, T9, T8, T7, T6, T5, T4, T3, T2, T1

Answer: C


NEW QUESTION # 13
Consider the following test strategies:
I. Consultative test strategy
II. Reactive test strategy
III. Analytical test strategy
IV. Process-compliant test strategy
Consider also the following examples of test activities:
1. Prioritize the test cases, based on the results of a FMEA analysis, to ensure early coverage of the most important areas and discovery of the most important defects during test execution
2. Execute usability testing driven by the guidance of a sample of users (external to the test team)
3. Perform exploratory testing sessions throughout the system test phase
4. On an Agile project, execute tests that cover the test conditions identified for each user story of a feature planned for an iteration Which of the following correctly matches each test strategy with an appropriate example?

  • A. I-1; II-2; III-3; IV-4
  • B. I-3; II-2; III-1; IV-4
  • C. I-2; II-3; III-1; IV-4
  • D. I-2; II-3; III-4; IV-1

Answer: C

Explanation:
Section: Test Management
Explanation:


NEW QUESTION # 14
You are a Test Manager working for a software organization where reviews have never been applied. After a meeting with your managers examining a business case for reviews, (including their costs, benefits, and potential issues), the management finally decides to adopt formal reviews for future projects.
You have been given a budget that you have spent to provide training in the review process and to introduce the review process on a pilot project.
On that pilot project the introduction of reviews has been very positive in terms of positive involvement from all the participants. All the reviews applied to different documents have been very effective for their purposes (especially at revealing defects).
Which of the following answers describes an important success factor for the introduction of formal reviews which is missing in this scenario?

  • A. Training in the review process
  • B. Participant support
  • C. Definition and use of metrics to measure the ROI (Return On Investment)
  • D. Management support

Answer: C

Explanation:
Section: Reviews
Explanation/Reference:


NEW QUESTION # 15
One of your team members is struggling to identify the requirements to be tested for a project The requirements documents are not conventional but you have determined that the data is there.If they do some digging to find it Given this information in what competence area does this person need to improve?

  • A. Methodical competence
  • B. Social competence
  • C. Professional competence
  • D. Personal competence

Answer: A

Explanation:
* Competence in Handling Non-Standard Requirements:
* Methodical competence refers to the ability to systematically analyze and interpret information, even when it is unconventional or unstructured.
* The tester needs to refine their skills in identifying and deriving testable requirements from the available data.
* Evaluation of Options:
* A(Professional competence) refers to domain knowledge but does not address the specific challenge.
* Bis correct as it pertains to systematically working through unconventional requirements.
* C(Social competence) andD(Personal competence) do not address the analytical challenge.
References and Syllabus Alignment:
* Methodical competence is emphasized under "Test Management Skills" in the ISTQB syllabus (TM-
3.1.1).


NEW QUESTION # 16
You feel that your team has become lazy when applying good software testing techniques You have given each of them a challenge to take a different business rule and build a full decision table and then collapse that table You will then assess the results For this assessment, whatcompetencies are you validating?

  • A. Social and personal
  • B. Methodical and personal
  • C. Professional and social
  • D. Professional and methodical

Answer: D

Explanation:
* Competence Assessment:
* Professional competenceis validated by understanding and applying testing techniques to create a decision table.
* Methodical competenceis validated by systematically collapsing the decision table to ensure efficient test case design.
* Evaluation of Options:
* BandCinvolve social and personal skills, which are unrelated to the task.
* Dmisses the professional aspect of understanding business rules.
* Ais correct because the challenge tests both professional knowledge and methodical skills.
References and Syllabus Alignment:
* Decision table techniques and testing competencies are emphasized in "Test Techniques" (TM-1.4.1) and "Test Team Skills" (TM-3.1.1).


NEW QUESTION # 17
Consider the following test strategies:
I. Consultative test strategy
II. Reactive test strategy
III. Analytical test strategy
IV. Process-compliant test strategy
Consider also the following examples of test activities:
1. Prioritize the test cases, based on the results of a FMEA analysis, to ensure early coverage of the most important areas and discovery of the most important defects during test execution
2. Execute usability testing driven by the guidance of a sample of users (external to the test team)
3. Perform exploratory testing sessions throughout the system test phase
4. On an Agile project, execute tests that cover the test conditions identified for each user story of a feature planned for an iteration
Which of the following correctly matches each test strategy with an appropriate example?

  • A. I-1; II-2; III-3; IV-4
  • B. I-3; II-2; III-1; IV-4
  • C. I-2; II-3; III-1; IV-4
  • D. I-2; II-3; III-4; IV-1

Answer: C

Explanation:
Explanation/Reference:
Explanation:


NEW QUESTION # 18
Which of the following is an example of the test closure activity indicated as "lessons learned"?

  • A. Deliver a list of the open defects of a software product released into production to the service desk team
  • B. Archive all the test results of the acceptance testing phase
  • C. Participate in a meeting at the end of a project aimed at better managing the events and problems of future projects
  • D. Deliver an automated regression test suite, used during the system test phase of a software product released into production, to the team responsible for maintenance testing

Answer: C

Explanation:
Explanation/Reference:
Explanation:


NEW QUESTION # 19
Assume that you are the Test Manager for a small insurance application development project.
You have decided to adopt a risk-based testing strategy: 5 product risks (R1, R2, R3, R4, R5) have been identified and their levels of risk have been assessed. 10 test cases (T1, ..., T10) have been designed to cover all the product risks.
The following table shows the risk level and the test cases associated to the identified product risks (higher risk level means higher risk):

You are not confident with the assessment of the risk level and you suspect that it will be possible to find high- priority bugs in low-risk areas.
Furthermore the period for test execution is very short. Your goal is to test all the product risks in a risk-based way, while assuring that each product risk gets at least some amount of testing.
Which of the following answers describes the best test execution schedule in this scenario?

  • A. T1, T2, T3, T4, T5, T6, T7, T8, T9, T10
  • B. T10, T8, T6, T4, T2, T9, T7, T5, T3, T1
  • C. T1, T3, T5, T7, T9, T2, T4, T6, T8, T10
  • D. T10, T9, T8, T7, T6, T5, T4, T3, T2, T1

Answer: C

Explanation:
Section: Testing Process
Explanation/Reference:


NEW QUESTION # 20
In the test strategy document your organization declares:
- To adopt a V-model development lifecycle, with three formal levels of testinG. unit,
integration and system testing
- To use a blended risk-based and regression-averse testing strategy for each level of
testing
The following is an excerpt of the "approach" section for the system test plan document of a
new project:
"Testing will only use manual tests. Due to the short period of time for test execution, the
following activities will be performed in parallel with test execution: Test planning, test
analysis and test design.
Basic metrics will be taken for test effort (i.e. person-hours), test cases executed
(passed/failed), and incidents (no more metrics, such as code coverage, will be collected)."
In the system test plan, no deviations from the test strategy are described.
Based only on the given information, which of the following statements is true?
K4 3 credits

  • A. The approach described in the system test plan document is consistent with the risk-
    based testing strategy, but it is inconsistent with the regression testing strategy
  • B. The approach described the system test plan document is inconsistent with both the
    risk-based and regression testing strategies
  • C. The approach described in the system test plan document is consistent with the test
    strategy
  • D. The approach described in the system test plan document is consistent with the
    regression testing strategy, but it is inconsistent with the risk-based testing strategy

Answer: B


NEW QUESTION # 21
The following are the exit criteria described in the test plan of a software product:
EX1. The test suite for the product must ensure that at least each quality risk item is covered by at least one test case (a quality risk item can be covered by more test cases).
EX2. All test cases in the test suite must be run during the execution phase.
EX3. Defects are classified into two categories: "C" (critical defect) and "NC" (non-critical defect). No known C defects shall exist in the product at the end of the test execution phase.
Which of the following information is useless when the specified exit criteria is evaluated?

  • A. A list of all the open defects with the associated classification information extracted from the defect tracking system
  • B. A traceability matrix showing the relationships between the product risk items and the test cases
  • C. A chart, showing the trend in the lag time from defect reporting to resolution, extracted from the defect tracking system
  • D. The execution status of all the test cases extracted from the test management tool

Answer: C

Explanation:
Section: Testing Process
Explanation/Reference:


NEW QUESTION # 22
Consider the following skills assessment spreadsheet for your test team (consisting of four
team members):
This spreadsheet has three sections: technical expertise, testing skills and professionalism.
The skill levels for each skill area for both the "technical expertise" and "testing skills"
sections have been rated on a four-point scale:
- E (Expert): indicates that a person has expert knowledge and experience in the skill area
- B (Beginner): indicates that a person has some knowledge and experience in the skill
area but he/she is not autonomous
- W (Wants to learn): indicates that a person has no knowledge or experience in the skill
area but he/she wants to learn that skill
- NI (Not Interested): indicates that a person has no knowledge or experience in the skill
area and he/she is not interested to learn that skill
The skill levels for each skill area of the "professionalism" section have been rated on a
three point scale (H=High, M=Medium, L=Low).
Consider the following analysis of testing skills performed on four peoplE. Alex, Robert,
John and Mark (all the skills have been rated on an ascending scalE. The higher the score,
the better the skill):

Which of these people, based on this analysis, would you expect to be most suitable to
work specifically as test designer?
K4 3 credits

  • A. Alex
  • B. Mark
  • C. Roberta
  • D. John

Answer: C


NEW QUESTION # 23
Which of the following best describes the appraisal costs in the cost of quality'

  • A. The cost spent preventing defects from occurring in the first place
  • B. The cost for performing dynamic testing
  • C. The cost for fixing defects
  • D. The cost for lawyers to deal with a lawsuit over a defect

Answer: B

Explanation:
* Definition of Appraisal Costs:
* Appraisal costs include expenses related to evaluating and testing the product to detect defects before release.
* These include costs for dynamic testing, reviews, inspections, and validation activities.
* Evaluation of Options:
* Arefers to prevention costs, not appraisal.
* Bis correct because dynamic testing is an appraisal activity.
* Crefers to failure costs (internal/external), not appraisal.
* Drelates to legal failure costs.
References and Syllabus Alignment:
* Appraisal costs are outlined under "Cost of Quality" in ISTQB syllabus (TM-2.1.1).


NEW QUESTION # 24
Assume you are the Test Manager in charge of independent testing for avionics applications.
You are in charge of testing for a project to implement three different CSCI (Computer Software Configuration Item):
- a BOOT-X CSCI that must be certified at level B of the DO-178B standard
- a DIAG-X CSCI that must be certified at level C of the DO-178B standard
- a DRIV-X CSCI that must be certified at level A of the DO-178B standard These are three different software modules written in C language to run on a specific hardware platform.
You have been asked to select a single code coverage tool to perform the mandatory code coverage measurements, in order to meet the structural coverage criteria prescribed by the DO-178B standard. This tool must be qualified as a verification tool under DO-178B.
Since there are significant budget constraints to purchase this tool, you are evaluating an open-source tool that is able to provide different types of code coverage. This tool meets perfectly your technical needs in terms of the programming language and the specific hardware platform (it supports also the specific C-compiler).
The source code of the tool is available.
Your team could easily customize the tool to meet the project needs. This tool is not qualified as a verification tool under the DO-178B.
Which of the following are the three main concerns related to that open-source tool selection?

  • A. Does the tool require a system with more than 4GB of RAM memory?
  • B. What are the costs to qualify the tool as a verification tool under the DO-178B?
  • C. Does the tool support all the types of code coverage required from the three levels A, B, C of the DO-178B standard?
  • D. Is the installation procedure of the tool easy?
  • E. Does the tool have a good general usability?
  • F. Is the licensing scheme of the tool compatible with the confidentiality needs of the avionics company?

Answer: B,C,F

Explanation:
Section: Test Tools and Automation
Explanation/Reference:


NEW QUESTION # 25
You tend to be conservative in your project estimations because you know how many things can go wrong and extend the schedule. You manager is not happy with your estimates and thinks you are being too negative with your numbers and not trying hard enough Which estimation method should you use to provide your manager with a positive' number while still also providing the number you think is more realistic?

  • A. Planning poker
  • B. Extrapolation
  • C. Three-point estimation
  • D. Wideband defphi

Answer: C

Explanation:
* Context Analysis:
* The manager perceives conservative estimates as overly negative. The goal is to balance optimism with realism to satisfy both the team and the manager.
* Three-point estimation provides a range of estimates: optimistic, pessimistic, and most likely, addressing the need for a positive yet realistic projection.
* Evaluation of Options:
* A. Wideband Delphi:
* Involves group-based estimation using consensus techniques. While reliable, it does not explicitly offer optimistic vs. realistic estimates.
* B. Planning Poker:
* Often used in Agile projects, this technique involves relative estimation but does not inherently provide optimistic and pessimistic figures.
* C. Three-point estimation:
* Correct. Combines optimistic, pessimistic, and realistic estimates to calculate a weighted average. This allows presentation of both realistic and "positive" numbers to the manager.
* D. Extrapolation:
* Based on past data trends but does not offer a range of estimates or a way to address manager concerns directly.
* Syllabus Alignment:The ISTQB syllabus mentions estimation methods like three-point estimation as effective techniques for providing balanced and transparent project timelines (TM-2.2.1).
References:
* ISTQB Advanced Level Test Management Syllabus


NEW QUESTION # 26
In your organization the following tools of the same vendor are currently in usE. a
requirements management tool, a test management tool and a bug tracking tool.
You are the Test Manager.
You are currently evaluating a test automation tool of the same vendor (to complete the
vendor's tool suite) against an interesting open-source test automation tool under the GNU
GPL (General Public License).
There are no initial costs associated to that open-source tool.
Which of the following statements associated to the selection of the open-source tool is
correct in this scenario?
K2 1 credit

  • A. The open-source tool can be modified but it can't be distributed further in any way
  • B. There are no initial costs for the open-source tool but you should carefully consider the
    costs associated to the integration with the existing tools and also evaluate the recurring
    costs
  • C. There are no initial costs for the open-source tool because open-source tools are usually
    low-quality, while vendor tools have always a better quality than the corresponding open-
    source tools
  • D. The open-source tool can be modified but only if the community of developers of that
    tool gives you the formal permission to modify it

Answer: B


NEW QUESTION # 27
......


ISTQB ATM (ISTQB Certified Tester Advanced Level - Test Manager [Syllabus 2012]) Exam is a highly respected certification program designed for software testing professionals who want to advance their skills in test management. Advanced Test Management Exam v3.0 - ISTQB certification program is offered by the International Software Testing Qualifications Board (ISTQB), which is a non-profit organization that aims to promote software testing as a profession.

 

100% Free ATM Daily Practice Exam With 52 Questions: https://www.validdumps.top/ATM-exam-torrent.html

Pass ATM Review Guide, Reliable ATM Test Engine: https://drive.google.com/open?id=15cQshqy3avSLSKEzxL2_Yc4Z8p5NK8b5