[Q79-Q95] Certification Training for PRINCE2Foundation Exam Dumps Test Engine [2021]

Share

Certification Training for PRINCE2Foundation Exam Dumps Test Engine [2021]

Oct 04, 2021 Step by Step Guide to Prepare for PRINCE2Foundation Exam

NEW QUESTION 79
Which is a typical core activity within configuration management?

  • A. Status accounting
  • B. Communication
  • C. Assessment
  • D. Quality control

Answer: A

 

NEW QUESTION 80
Which is NOT undertaken during the Initiating a Project process?

  • A. Show how the outcome is to be achieved
  • B. Appoint an Executive and Project Manager
  • C. Identify if the project is sufficiently aligned with corporate objectives
  • D. Review why the project is needed

Answer: B

 

NEW QUESTION 81
Which is an objective of the Directing a Project process?

  • A. Provide accurate progress information to the Project Manager
  • B. Create and authorize the project mandate
  • C. Control the day-to-day running of the project
  • D. Provide management control and direction

Answer: D

 

NEW QUESTION 82
Which is a purpose of an Exception Plan?

  • A. Define the changes which are within the scope of the change budget
  • B. Reduce the number of exception assessments, by agreeing a budget to cover the costs of any requests for change
  • C. Identify the actions required to recover from the effect of a tolerance deviation
  • D. Show the reason for the tolerance deviation from a Stage Plan or Project Plan

Answer: C

 

NEW QUESTION 83
Which is assumed to be a customer's responsibility in the PRINCE2 customer/supplier environment?

  • A. Ensure the technical integrity of a project
  • B. Specify the desired result
  • C. Provide the resources and skills to deliver the desired result
  • D. Develop a project's products

Answer: B

 

NEW QUESTION 84
Which is a purpose of the 'directing a project' process?

  • A. To delegate day-to-day management of the project to the project manager
  • B. To control the day-to-day running of the project
  • C. To create and authorize the project mandate
  • D. To ensure that work on products allocated to the team is authorized and agreed

Answer: A

Explanation:
Reference: https://www.prince2primer.com/directing-a-project-in-prince2/

 

NEW QUESTION 85
Which is an objective of the Starting up a Project process?

  • A. Agree how the project will be monitored and controlled after initiation
  • B. Authorize the Project Manager to proceed with the initiation stage
  • C. Identify who will be responsible for creating the Project Plan
  • D. Agree how issues and changes will be identified, assessed and controlled

Answer: C

 

NEW QUESTION 86
Which process is triggered towards the end of the final stage when all the assigned work has been completed?

  • A. Managing Product Delivery
  • B. Closing a Project
  • C. Managing a Stage Boundary
  • D. Controlling a Stage

Answer: B

Explanation:
Section: Volume A

 

NEW QUESTION 87
Which is a purpose of the Controlling a Stage process?

  • A. Produce a Team Plan for the work to be assigned to a Team Manager
  • B. Select and implement actions that will resolve deviations from a plan within tolerance
  • C. Obtain approvals for products delivered in a Work Package
  • D. Update a Project Plan to incorporate the actuals from a Stage Plan

Answer: B

 

NEW QUESTION 88
What should be considered when defining the number of management stages in a project?

  • A. When project support will be available
  • B. When key decisions need to be made
  • C. When the team managers are available
  • D. When highlight reports will be submitted

Answer: B

Explanation:
Section: Volume B
Explanation/Reference: https://www.prince2primer.com/prince2-management-and-technical-stages/

 

NEW QUESTION 89
Which is a responsibility of a Team Manager?

  • A. Ensuring delivery of products in the Managing Product Delivery process
  • B. Setting WorkPackage tolerances
  • C. Producing Highlight Reports for the Project Manager
  • D. Reviewing the status of the stage

Answer: A

 

NEW QUESTION 90
What product is used to maintain a record of those who have an interest in the project and their information requirements?

  • A. Project Plan
  • B. Project Product Description
  • C. Project Brief
  • D. Communication Management Strategy

Answer: D

 

NEW QUESTION 91
Which is a purpose of a Project Product Description?

  • A. Records the costs and timescales for delivery of the project's final product
  • B. Provides a list of all the products to be delivered by the project
  • C. Shows the dependencies between the project's products to aid planning
  • D. Defines what the project must deliver in order to gain acceptance

Answer: D

 

NEW QUESTION 92
Identify the missing words in the following sentence.
The 'directing a project' process starts when [ ? ] and is triggered by the request to initiate a project.

  • A. the project board has agreed the project strategies
  • B. the 'starting up a project' process is completed
  • C. corporate, programme management or the customer have authorized a project
  • D. the project mandate has been approved by the project board

Answer: B

Explanation:
Explanation/Reference:
Reference https://www.siliconbeachtraining.co.uk/blog/prince2-directing-project-process-dp

 

NEW QUESTION 93
Who should act as the communication channel between a project and corporate or programme management?

  • A. Project Assurance
  • B. Project Board
  • C. Project Support
  • D. Project Manager

Answer: B

 

NEW QUESTION 94
Which is a minimum requirement for applying the change theme?

  • A. To identify whether an issue affects the continuation of the project
  • B. To tailor all changes to improve the quality of the project
  • C. To produce a breakdown of the products to be produced
  • D. To ensure each change is managed as an exception

Answer: D

 

NEW QUESTION 95
......

Ultimate Guide to Prepare PRINCE2Foundation Certification Exam for PRINCE2 Certification: https://www.validdumps.top/PRINCE2Foundation-exam-torrent.html

PRINCE2 Certification PRINCE2Foundation Real Exam Questions and Answers FREE Updated: https://drive.google.com/open?id=1sKA8opmzrDpqkkVWyO0qhIlfyELMeqL7