Use PRINCE2 PRINCE2Practitioner Dumps To Succeed Instantly in PRINCE2Practitioner Exam [Q141-Q165]

Share

Use PRINCE2 PRINCE2Practitioner Dumps To Succeed Instantly in PRINCE2Practitioner Exam

Ultimate Guide to PRINCE2Practitioner Dumps - Enhance Your Future Career Now


PRINCE2 Practitioner certification exam is highly regarded in the project management industry and is recognized globally. PRINCE2 Practitioner Exam certification demonstrates that the holder has the knowledge and skills required to manage projects using the PRINCE2 methodology. PRINCE2 Practitioner Exam certification is highly valued by organizations that use PRINCE2 methodology in their project management approach, making the PRINCE2 Practitioner certification a highly sought-after qualification for project managers. The PRINCE2 Practitioner certification exam is challenging, and candidates are required to have extensive knowledge and practical experience in project management to pass the exam.


PRINCE2 Practitioner certification exam is a globally recognized certification that demonstrates a candidate's ability to apply the principles of PRINCE2 project management methodology in real-world scenarios. PRINCE2 Practitioner is an advanced level certification that builds upon the foundation laid by the PRINCE2 Foundation certification. It is the second level of certification in the PRINCE2 certification pathway.

 

NEW QUESTION # 141
Additional Information

Further information on some resources who could be involved in the project:
Outcome Account Manager: He represents Outcome which is a recruitment agency that provides specialist outsourcing resources. Outcome provided the consultants who carried out the feasibility study and the same consultants will be providing support and guidance to the Information Technology and Facilities teams during the project.
Director of Finance Division: She was transferred from the Information Technology Division 12 months ago. She is responsible for ensuring a cost-conscious approach is adopted in all operational and project activities across the Ministry of Food Hygiene.
Hardware Manager: Reports to the Director of Information Technology. He provides computer hardware to all business functions but has little awareness of the needs of his colleagues working in software.
Payroll Manager: Reports to the Director of Finance. He is a very experienced and efficient qualified accountant who has much of the responsibility of running the Finance Division on behalf of the Director of Finance. He has been involved in drafting the Ministry's business strategy and assisting in a full business risk assessment. He also drafted the corporate Business Case standards.
Which 2 alternative actions apply to the proposed Senior Supplier for this project?

  • A. Remove because she only represents the Information Technology Division.
  • B. Replace with 'Director of Facilities' because he supports the initiative and has many ideas about how to improve the service.
  • C. Retain because she is responsible for the design of the future Information Technology organization and working practices.
  • D. Add 'Director of Facilities' because he is responsible for the design of the future organization, processes, systems and operation models for Facilities.
  • E. Add 'Hardware Manager' because he provides computer hardware to all business functions and will be impacted by the outcome.

Answer: C,D


NEW QUESTION # 142
While preparing the Quality Management Strategy, the Project Manager noticed that the corporate quality management system does not specifically cover project management.
Which option provides an appropriate way for the Project Manager proceed?

  • A. Record the development of a corporate quality management system for project management as a prerequisite of the Project Plan.
  • B. Seek relevant organizational standards, then facilitate a workshop to discuss the Quality Management Strategy with Project Assurance.
  • C. Proceed with the project without a Quality Management Strategy and adopt the selected service provider's standards in stage 4.

Answer: B


NEW QUESTION # 143
Starting Up a project is triggered by which of the following?

  • A. Mandate
  • B. Legislation
  • C. Corporate Strategy
  • D. Risks

Answer: A


NEW QUESTION # 144
The Training Delivery Manager was identified as the senior user. However, before the project begins, this manager goes on long-term sick leave. The executive says that they do not need to replace the role of senior user on the project board.
Is this an appropriate application of the 'defined roles and responsibilities' principle, and why?

  • A. No, because trainers need to be represented on the project board to ensure the outcomes meet the trainers' needs.
  • B. Yes, because having two out of three of the stakeholder interests represented on the project board is enough.
  • C. No, because the resources and expertise required by the project may be internal or external.
  • D. Yes, because the executive can ensure that the investment provides value for money.

Answer: B

Explanation:
Explanation/Reference: http://prince2.wiki/Define_roles_and_responsibilities


NEW QUESTION # 145
The project is in stage 2. The project manager is reviewing stage status and has collected the checkpoint reports from the team managers. These show that the products are being completed on schedule.
However, project support has raised issues that quality reviews have not been completed as agreed. The project manager reports in the highlight report that the stage is progressing well.
Is this appropriate, and why?

  • A. Yes, because the highlight report is used to provide the project board with stage and project progress.
  • B. Yes, because the highlight report is a summary of the information in the checkpoint reports.
  • C. No, because the project manager should have recorded the cause of the delay to the quality reviews in the lessons log.
  • D. No, because the issues raised by project support are a cause for concern and should be reflected in the highlight report.

Answer: D


NEW QUESTION # 146
The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.
Which 2 statements should be recorded under the Risk management procedure heading?

  • A. When a new problem arises, a full impact analysis will be undertaken to assess the impact on the project' objectives and Business Case.
  • B. 'Reduce' Response actions which result in a lower impact and/or probability rating.
  • C. Every threat and opportunity identified must be clearly defined in terms of cause, event and effect.
  • D. Probability will be assessed against the scales defined in this Risk Management Strategy.
  • E. Any risk which has an expected value of more than E1 k will NOT be registered.

Answer: C,D


NEW QUESTION # 147
Project Scenario - Health and Safety Training Project:
ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.
ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e-learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.
The e-learning course will be developed by a specialist external consultancy. The materials for classroom- based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.
The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered. ABC Company is planning to deliver pilot courses within five months of starting the project.
The ABC Company standard development model for new courses recommends the following stages:
End of the Project scenario.
Additional Information:
The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.
The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.
The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.
The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.
The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.
The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.
The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.
The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.
The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.
The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him.
They promote existing training courses to other training companies and existing customers.
End of the additional information.
At the end of stage 2, the specialist 'e-learning course' supplier will be selected. As a result, it is decided that the quality management approach will not be created until the end of stage 2, to take into account this supplier's standards and techniques.
Is this appropriate, and why?

  • A. Yes, because the product description for each product will define the required quality approach within each stage.
  • B. Yes, because the quality management approach should take into account the supplier's standards, tools and techniques.
  • C. No, because the quality management approach should be created during the initiation stage and updated later.
  • D. No, because the quality management approach should be limited to ABC Company's quality standards.

Answer: B


NEW QUESTION # 148
Additional Information Product Description

Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any
changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider.
The service level agreement between MFH and the selected service provider will specify the type and quality of service required. The selected service provider must follow the industry standards for providing outsourced services.
MFH has a quality management system which contains a document control procedure for all its documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a
formal approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors)
Introduction
1.This document defines the approach to be taken to achieve the required quality levels during the project.
2.The Project Board will have overall responsibility for the Quality Management Strategy.
3.Project Assurance will provide assurance on the implementation of the Quality Management Strategy.
Quality management procedure - Quality standards
4.The selected service provider will operate to industry standards for providing outsourced services.
5.MFH document standards will be used.
Records
6.A Quality Register will be maintained to record the planned quality events and the actual results from the quality activities.
7.Configuration Item Records will be maintained for each product to describe its status, version and variant.
8.Approval records for products that require them will be stored in the quality database. Roles and responsibilities
9.The DIT will check that the employment contracts for outsourced staff adhere to employment law.
10.
Team Managers will provide details of quality checks that have been carried out.
11.
Team Managers will ensure that the Quality Register is updated with the names of team members who are involved in the review process.
12.
The Senior User will review the Product Descriptions of the products to be produced by the selected service provider to ensure that they can be achieved.
Which statement applies to the Roles and responsibilities section?

  • A. Amend entry 12 because this is the responsibility of supplier assurance.
  • B. Delete entry 11 because only the Project Manager can update the Quality Register.
  • C. Delete entry 9 because this should only be recorded in the Product Description.
  • D. Delete entry 10 because this is the responsibility of the quality review chair.

Answer: A

Explanation:
Topic 5, Plans Theme


NEW QUESTION # 149
The project board has asked user and supplier assurance to review all product descriptions relating to the
'updated corporate quality procedures', prior to authorizing the stage plan for stage 3.
Is this appropriate as part of the 'directing a project' process, and why?

  • A. Yes, because project assurance should review the stage 3 plan for viability, if requested by the project board.
  • B. Yes, because project assurance should assess whether all stakeholders have been identified, if requested by the project board.
  • C. No, because the project manager is responsible for writing product descriptions when creating the stage 3 plan.
  • D. No, because the project board should review new product descriptions before they authorize the stage 3 plan.

Answer: D


NEW QUESTION # 150
When examining a project issue, which three aspects should be considered?
1. Performance targets
2. Business Case
3. Resources
4. Risk

  • A. 1, 3, 4
  • B. 1, 2, 3
  • C. 2, 3, 4
  • D. 1, 2, 4

Answer: D


NEW QUESTION # 151
While planning the initiation stage, the Project Manager reviewed some threats that had been recorded in the Daily Log.
Which threat should have been assessed for possible risk responses to be included in the Initiation Stage Plan?

  • A. There is a shortage of service providers so there is a possibility that no suitable service providers respond to the request for proposals. This would prevent the Outsourcing project from proceeding.
  • B. The Project Brief is a complex document and may not be approved by the Executive.
  • C. MFH has no experience in outsourcing and this may affect understanding of what is required, resulting in inadequate plans and strategies.

Answer: A


NEW QUESTION # 152
During which of the following activities is the Project Product Description created?

  • A. Design and appoint the Project Management Team
  • B. Plan the initiation stage
  • C. Select the project approach and assemble the project brief
  • D. Prepare the outline business case

Answer: D


NEW QUESTION # 153
The project has a cost tolerance of +5% I .5%, of which stage 2 has a tolerance of +£45k 1-£45k.
Lines 1 to 6 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.

Answer:

Explanation:

Explanation


NEW QUESTION # 154
Which of the following statements are True:
1. Quality management is the complete set of quality standards, procedures and responsibilities for a site or organization.
2. Quality planning is about defining products required of the project with their respective quality criteria, methods and responsibilities.
3. Quality control focuses on the operational techniques and activities used to carry out quality inspections
4. Quality assurance ensures that quality methods are being correctly followed.

  • A. 2, 3 & 4
  • B. 1, 3 & 4
  • C. 1, 2 & 4
  • D. 1, 2 & 3

Answer: D


NEW QUESTION # 155
Which of the following statements is FALSE regarding the Continued Business Justification?

  • A. The justification for the project may change.
  • B. If the project is no longer justified it should be stopped.
  • C. The justification for the project should remain vabd.
  • D. The justification for the project must remain the same throughout the project.

Answer: C


NEW QUESTION # 156
HOTSPOT
The project has a cost tolerance of +5% I *5%, of which stage 2 has a tolerance of +(GBP)45k 1(GBP)45k.
Lines 1 to 6 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.

Answer:

Explanation:

Topic 6, Risk Theme


NEW QUESTION # 157
HOTSPOT
Scenario
Additional Information
During the initiation stage the Project Manager met with the Marketing Director to find out more about the requirements of the promotional calendar and recorded the following notes:
There has been a reduction in the order numbers at the MNO Manufacturing due in part to the increased marketing activities of its competitors. 10% of customers have not re-ordered in this financial year and staff morale is poor. A number of skilled staff have left as a result and replacement staff have not been recruited due to the reduced operation. If the project is successful, a recruitment campaign will be required to fill the existing staff vacancies and there may be a requirement for additional staff. Operational costs are likely to increase because skilled staff are expensive and difficult to find.
In financial terms, there were a total of 1,500 orders in the last financial year, each with an average profit of (GBP)2k. The Marketing department believes that sending a promotional calendar to our current and prospective customers would increase orders by at least 10% with a minimum of 10 further orders from the list of prospective customers within 12 months from the date of distribution.
The Marketing Director will be funding the project from the business marketing budget. She believes that the effect of a good company image portrayed by a successful calendar would last into a second year. She has forecast the same increase in orders for a second year and predicts that the annual employee satisfaction survey will show a measurable improvement in staff morale.
A number of alternatives were explored, including:
20% discount for all repeat customers - not cost-effective and very short term A promotional calendar as a free Christmas gift - would target current and prospective customers and the benefits would last into a second year A series of television and press advertisements* was too expensive A direct mail shot to all customers - benefit would be short term Creation of an internet website - would not suit all customers
The calendar is seen as the favored option, as long as the company's competitors do not increase their marketing activity. Whilst the Marketing department wants a very high quality, glossy product, the project management team must be aware of the cost this will incur.
Using the Project Scenario and the additional Information provided for this question
-- ---
In the Scenario Booklet, answer the following question.
Lines A to E in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.

Answer:

Explanation:


NEW QUESTION # 158
Which statement is an appropriate entry for the Initiation Stage Plan?

  • A. The plan is based on the external outsourcing consultants being available at the start of the initiation stage.
  • B. The initial project cost estimate of (GBP)2.5m, will have a tolerance of +(GBP)125k J(GBP)75k.
  • C. The Daily Log has been updated with the new risks which were identified while preparing the Initiation Stage Plan.
  • D. The project management team will consist of representatives from the IT and Facilities Divisions.

Answer: A


NEW QUESTION # 159
Additional Information
Extract from the Communication Management Strategy.
The project information in the table below is true, but it may not be recorded under the correct heading or be in the correct document.

Using the Project Scenario, select the appropriate response to each of the following 5 questions which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a relatively simple project, the Project Manager combined the Starting Up a Project process and the Initiating a Project process. No Project Brief has been produced. Instead the Project Manager used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO includes the Business Case, a product checklist and several Product Descriptions, Including the Project Product Description. Short sections are also included for each of the strategies and the controls to be applied. The Project Manager has elected to use the Daily Log to record all risks, issues, lessons and quality results.
After the initiation stage there will be two further stages during which a small number of Work Packages will be authorized. While these are being managed, the Project Manager will hold regular checkpoints, which will support the production of weekly Highlight Reports to the Project Board.
There is no mention of any Stage Plans, yet there are two further stages proposed. How will this be resolved?

  • A. It is appropriate for the Calendar project to be run as two further stages as there is a key decision to be made at the end of stage 2. Stage Plans will be produced.
  • B. There will be three Stage Plans, the two management stages plus an additional stage to plan and complete the activities of the Closing a Project process.
  • C. Whilst the activities are divided into two further stages, there is no reason why the Calendar project should use stages. The project will therefore be run as a single stage project and the activities will be added to the Initiation Stage Plan.

Answer: A


NEW QUESTION # 160
The project is at the end of stage 4. The project manager has changed the benefits management approach. It now includes all the activities necessary to measure the increased revenue.
Who should approve this update?

  • A. Project board
  • B. Project assurance
  • C. Project manager
  • D. Corporate management

Answer: A

Explanation:
Explanation


NEW QUESTION # 161
Which of the following activities could trigger the production of an exception plan?

  • A. Giving ad hoc direction
  • B. Report stage end
  • C. Escalating a project issue
  • D. Review Stage status

Answer: A


NEW QUESTION # 162
Scenario
A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure to cut costs, better manage suppliers' performance and reduce the confusion caused by inadequate internal controls, outdated standards and outdated technology. External consultants were employed to conduct a feasibility study to identify options to address the problems, and the likely costs and benefits. The following options were considered:
● Do nothing.
● Re-engineer selected business functions.
● Outsource selected business functions.
The feasibility study concluded that there was a case for outsourcing the MFH Information Technology Division and the Facilities Division (maintenance of buildings and grounds). The recommendations were:
● One service provider should be contracted to provide the services currently provided by the Information Technology Division and the Facilities Division.
● A 10-year service contract should be agreed with the selected service provider.
The feasibility study developed high-level designs of the current organization, processes, systems and operating models, plus an outline Business Case for the required project. The external consultants also made the following recommendations for the management of the project:
● Use PRINCE2.
● Set up the project with 4 management stages:
Stage 1. Standard PRINCE2 initiation activities.
Stage 2. Create detailed designs (future organization, processes, systems and operating models) and the service level agreement between MFH and the future service provider.
Stage 3. Request and evaluate proposals, select service provider and agree contract.
Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run trial period.
Initial estimates indicated that the project would cost £2.5m and take two years to complete.
MFH senior management agreed that there was a case for outsourcing, and accepted the recommendations as a basis for the project. There is an expected saving of £20m over 10 years.
The Outsourcing project has completed the Starting up a Project process and is now in the initiation stage.
Because of the strategic importance of the project, the MFH Chief Executive Officer has taken the role of Executive. A PRINCE2-experienced Project Manager has been appointed from within MFH. Staff within the business functions being outsourced will work with the external consultants who conducted the feasibility study to define the detailed designs.
Which 2 statements should be recorded under the Expected benefits heading?

  • A. The total expected savings over 10 years, at current prices, is £20m.
  • B. Outsourcing would allow MFH to take advantage of the best services the outsourcing industry has to offer.
  • C. The 10-year outsourcing contract will enable MFH to stabilize costs at agreed levels.
  • D. The 10-year outsourcing contract, at current prices, will be worth £80m.
  • E. The confirmed cost of the Outsourcing project is £2.5m, but with considerable savings over 10 years.

Answer: A,C

Explanation:
Explanation/Reference:
Reference: http://www.whatisprince2.net/prince2-theme-business-case.php


NEW QUESTION # 163
Which 2 statements should be recorded under the Expected dis-benefits heading?

  • A. The calendar may not result in the 10 further orders from the list of prospective customers in 12 months.
  • B. The calendar may not result in the expected 10% increase in orders.
  • C. A high quality, glossy product will involve additional costs.
  • D. Individuals in the engineering team who are not selected to appear in the calendar photographs will become
    de-motivated.
  • E. Because the Calendar project is a priority for the MNO Manufacturing Company, the delivery of other
    projects within the Marketing department will be delayed.

Answer: D,E

Explanation:
Explanation/Reference:


NEW QUESTION # 164
Project Scenario - Health and Safety Training Project:
ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.
ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e-learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.
The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.
The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered.
ABC Company is planning to deliver pilot courses within five months of starting the project.
The ABC Company standard development model for new courses recommends the following stages:

End of the Project scenario.
Additional Information:
The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.
The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.
The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.
The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.
The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.
The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.
The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.
The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.
The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.
The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.
End of the additional information.
CONTROLLING A STAGE
Here are three activities that take place during the 'controlling a stage' process. Which role (A-F) should carry out each activity? Choose only one role for each action. Each role can be used once, more than once, or not at all.

Answer:

Explanation:

Explanation


NEW QUESTION # 165
......